The Nigerian National Petroleum Company (NNPC) Limited has secured $1.5 billion in financing for the Ajaokuta-Kaduna-Kano (AKK) gas pipeline project, as it moves towards commencing gas supply to Abuja before the end of 2026.
The development is expected to advance the delivery of one of Nigeria’s major gas transportation infrastructure projects, designed to extend natural gas access to parts of the country that have historically had limited pipeline connectivity.
NNPC’s Group Chief Executive Officer, Bashir Ojulari, disclosed the financing arrangement in an interview with the News Agency of Nigeria, explaining that the company secured the funds based on the pipeline’s projected gas transportation volumes.
According to him, the project has reached 95 per cent completion, with the remaining work largely involving the completion of associated stations and connections to customers.
Ojulari said the company was targeting the commencement of gas supply to Abuja before the end of December, while Kaduna and Kano are expected to receive supplies in 2027.
The 614-kilometre AKK pipeline is designed to transport natural gas from Ajaokuta in Kogi State through Abuja and Kaduna to Kano, creating a major transmission route for supplying industries, power generation facilities and other gas consumers across the region.
Its completion is expected to improve access to natural gas for businesses and industries in the northern corridor, while supporting efforts to expand domestic gas utilisation.
For the power sector, the availability of additional gas infrastructure could create opportunities for improved fuel supply to gas-fired electricity generation facilities, although the actual benefits will depend on the availability of gas, supporting infrastructure and agreements with prospective customers.
The project also forms part of Nigeria’s wider strategy to utilise its natural gas resources for domestic industrial development, electricity generation and economic activities.
With the main pipeline largely completed, attention is now shifting towards the remaining facilities required to make the infrastructure operational and deliver gas to its intended customers.