The Federal Government announced that testing has commenced on the 700 megawatts Zungeru Hydroelectric Power Plant ahead of the evaluation of electricity from the facility to the national grid.

It also stated that the $1.3 billion project, located in Niger State, had been connected to the national grid, in contrast to claims in some quarters that the plant was not connected to the grid.

The Minister of Power, Adebayo Adelabu, disclosed this while providing answers to industry questions contained in a document released in Abuja by his Special Adviser, Strategic Communication and Media Relations, Bolaji Tunji.

The Zungeru Hydroelectric Power Plant is a major infrastructure project with the capacity to generate 700MW, making it the second-largest hydroelectric plant in Nigeria, behind the Kainji Dam.

Located in the Kaduna River, near the town of Zungeru in Niger State, the plant is to generate 2.64 billion kilowatts-hour of electricity annually, meeting nearly 10 percent of Nigeria’s domestic energy needs.

The plant provides flood control, irrigation water and fish breeding facilities and its construction partners include the consortium of Chinese firms (Sinohydro Corporation Limited and China National Electric Engineering Company).

Industry analysts say the project is expected to be a significant boost to Nigeria’s power generation and is to contribute to economic development in the region.

Providing answers to enquiries about the plant, Adelabu said the facility had been completed, adding that its concession process had also been completed.

He said, “The payments by the concessionaire have been made and the official handing over of this plant has been done to the concessionaire, which is Mainstream Energy Limited, who are the current operators of Kainji and Jabba hydroelectric power plants.

“The stage we are now in is technical handing over by the Chinese consultants that built the Zungeru hydroelectric power plant to the concessionaire. This is because there is a one-year defect liability, where these contractors need to be on the project site to ensure that whatever problem occurs within one year, they can fix it.

“They are working earnestly with the concessionaire and the Ministry of Power, together with the Bureau for Public Enterprise to ensure that we conclude the technical handover of the plant.

“I can tell you that the testing stage started yesterday, that the power generation at the plant started yesterday, and that it will last about one or two weeks, after which total production will start. And I can tell you with good authority that the Zungeru power plant can evacuate power. Therefore, it is complete disinformation to say it is not connected to the national grid.”

Recall that in May 2023, the Federal Government stated that it had connected the Zungeru Hydroelectric Power Plant to the national grid, giving a boost to Nigeria’s power generation.

The former Minister of Power, Abubakar Aliyu, had announced the connection of the plant to the grid during a send-forth ceremony organised by power sector officials for him, and the former Minister of State for Power, Goddy Jedy-Agba, in Abuja.

“I want to say that today the Zungeru Hydroelectric Power Plant has become a reality. We have today joined the grid with 700MW. The testing started last night and information has reached us, with a pictorial view of the meters showing that the 700MW has gone on the grid.

“Recall that the last two weeks we were there together with members of the National Assembly, including the Chairman, Senate Committee on Power. We all visited the site and we are now putting power on the grid,” Aliyu had stated.

Energy

Shell signs agreement to build gas pipelines in Oyo State

Published

on

Shell Nigeria Gas, SNG, and the Oyo State Government have signed an agreement to develop a gas supply and distribution infrastructure that will deliver gas to industrial and commercial users in the state.

A statement released on Friday by Shell Nigeria’s Media Relations Manager, Abimbola Essien-Nelson, disclosed that SNG will build and operate the gas distribution network, which will serve customers across Oyo State for 20 years.

According to the statement, the project will start with the construction of gas distribution infrastructure along a 15km pipeline route, adding that it will grow to deliver up to 60 million standard cubic feet of gas per day across the state.

Speaking at the signing ceremony, the Oyo State Governor Seyi Makinde, described the project as a catalyst for development in the state.

The Managing Director of SNG, Ralph Gbobo, noted that the agreement was “a significant milestone for SNG and Oyo State to boost economic activities in Nigeria by supplying industries and manufacturers with natural gas, a more reliable, cost-efficient and environmentally friendly source of energy.”.

He explained that the project would boost Oyo State’s internal revenue and create Job opportunities for indigenes.“

“The Managing Director of The Shell Petroleum Development Company of Nigeria Limited and Chairman, Shell Companies in Nigeria, Osagie Okunbor, remarked that the event pointed to the value of partnership as “Shell continues to power progress” in Nigeria through more and cleaner energy solutions for commercial and industrial customers.

Continue Reading

Energy

Nigeria ripe for nuclear power to boost electricity generation – NAEC 

Published

on

The Nigeria Atomic Energy Commission (NAEC) in collaboration with Centre for Energy Research and Training (CERT), Ahmadu Bello University (ABU), Zaria would deploy nuclear science and technology to strengthen electric power generation in Nigeria.

Prof. Yusuf-Aminu Ahmed, Chairman NAEC disclosed this during the 20th Anniversary Symposium of the Nigeria’s first Nuclear Research Reactor-1 (NNR-1) in Zaria on Thursday.

Ahmed said the experience developed over the years on nuclear power at the centre makes Nigeria ripe and ready to go into the next level of power generation through the nuclear reactor.

“We have used the reactor for research and development over the years and now we are going to use the reactor for the purpose of generating electricity.

“President Bola Tinubu has already given the commission a mandate to see how it contributes in the clean energy sphere of Nigeria and the nuclear energy programme of Nigeria would participate,’’ Ahmed said.

He explained that the time for the project would not be open for the public; however, Ahmed added that international partners and vendors were working closely with the commission over the project.

He also said that intergovernmental agreements were signed with some of the vendors on the nuclear power in Nigeria and very soon President Tinubu would make an announcement on the issue.

Earlier, Sen. George Akume, Secretary to the Government of the Federation said the 20 years of safe operation of the nuclear research reactor was an indication that Nigeria has joined the campaign for safe application of nuclear energy.

Akume, represented by his Special Assistant on Technical Issues, Prof. Bolaji Babatunde, added that since the centre had safely operated the nuclear research reactor for 20 years, it can also obtain a nuclear reactor for electricity generation.

According to him, the process of having a reactor that would generate electricity is similar to operating a nuclear research reactor.

“President Tinubu has re-echoed the need for having nuclear energy into the sources of electric power generation in Nigeria and Nigerians should look forward to this power.

“Electricity generated through nuclear energy is clean and safe except for human errors or natural causes such as the one that happened in Hiroshima,’’ he said.

Earlier, Prof. Sunday Jonah, Director of the center said the event was to celebrate 20 years of safe operation, maintenance and utilisation of the first Nuclear Research Reactor code named NNR-1.

However, in spite of the numerous gains at the centre over the years, the Director lamented over a plot by NAEC to wrestle the centre from the university through the proposed NAEC Bill 2022.

He explained that such a move would negate the dreams of the founding fathers that established the centre in universities because of the culture of research and development being promoted at designated universities.

Continue Reading

Energy

Alake unveils gender strategy for mining, steel sector

Published

on

The Minister of Solid Minerals Development, Dr Dele Alake, has unveiled a document for Women in Mining in Nigeria (WIMIN) strategy document.

Speaking at the event, he described the strategy as a significant mile stone in the sector.

He said that the move was a demonstration of the commitment of the Ministry of Solid Minerals Development (MSMD)‘ and Ministry of Steel Development in fostering diversity.

He said that the strategy is aimed at promoting gender equality and women‘s empowerment, adding that its focused on driving productivity for the nations‘ sustainable development.

“It also focuses on improving the opportunities for women to benefit from both sectors sustainably in policy, regulatory, operational, and commercial (large scale, medium scale, small scale, and artisanal levels), and value and supply chain roles.

“This strategy is not just a document but a call to action and a blueprint for all stakeholders to create a more inclusive and gender-balanced mining and steel sector.

“It provides a guideline and framework to guide both ministries, their agencies, and stakeholders to integrate gender equality and women’s empowerment priorities in their policies, programmes, and initiatives,” he said.

He acknowledged the indispensable contributions of women to the success and sustainability of the mining sector, saying that their talents, expertise, and perspectives are critical to the success and growth of the industry.

According to him, Nigeria is not immune from the biases perpetuated against women in these two sectors.

In addressing the situation, he said that the Federal Government has prioritised gender equity and female participation in its “Roadmap for the Growth and Development of the Nigerian Mining Industry.”

He said as part of the efforts of MSMD and Ministry of Steel Development to implement the roadmap, the Mineral Sector Support for Economic Diversification (MinDiver) engaged a consultancy to develop the gender strategy.

He said that to achieve the objectives of the strategy, its institutional capacity would be strengthened for effective gender mainstreaming.

He added that that women’s participation in leadership and governance roles within the mining sector and communities would be increased.

“Promoting women’s economic empowerment and rights and eliminating all barriers (structural and systemic) that hinder women’s meaningful participation, access and control over mining resources and benefits,” he said.

The Minister added that they were committed to building partnerships across a wide range of stakeholders in achieving the vision of the strategy.

He said that the WIMIN strategy was firmly rooted in the principles of equality, diversity, and empowerment, and  a call to action for stakeholders mobilisation toward a more inclusive and gender-balanced industry.

Earlier in her remarks, the National President of WIMIN, Dr Janet Adeyemi, described the launch of the strategy as an opportunity to galvanise support and implement actions to address the entrenched gender disparities within the mining and steel sectors.

Represented by the National Secretary, Mrs Emily Ofodile, she said that women within these industries continue to encounter multifaceted barriers that hinder their full participation and advancement.

On her part, the Permanent Secretary of MSMD, Dr Mary Ogbe, urged, women to be change agents at all levels, and urged all organisations to have gender focal persons to help in coordinating all related matters.

Continue Reading

Trending