Top Story

FG terminates road contracts over alleged non-performance

Published

on

By Matthew Denis

The Federal Ministry of Works has terminated contract numbers 6,136, 6,137 and 6,138 with Mothercat Ltd, Dantata & Sawoe Construction Ltd and RCC Ltd, respectively.

The projects affected by the termination are the dualisation of Obajana – Benin road, section II (Okene – Auchi) in Kogi/Edo State; the dualisation of Obajana – Benin road, section III (Auchi – Ehor) in Edo State and the dualisation of Obajana – Benin road section IV (Ehor – Benin) in Edo State.

This was contained in a statement released by Orji Uchenna Orji, Special Adviser (Media) to the Minister of Works on Monday.

According to the government, the termination became necessary in view of the alleged inordinate delay by the affected companies in job performance and their failure, neglect and refusal to fulfil their contractual obligations as required by the Standard Conditions of Contract.

Orji stated that this had affected the timely completion of the projects and thus resulted in the expiration of the contracts by effluxion of time.